Saturday, December 11, 2010

SNOW!

Unseasonable cold and now a little snow is not helping us.  It is too cold for the masons to work, since the mortar will not set up properly.  Well digging continues and some interior work does too.  Temporary indoor heat will be installed as soon as the windows are completed.  More pictures at Our Picture Albums

Saturday, December 4, 2010

Windows on the west side!

We are starting to close up the southern wing of the building now.  Here you can see recently installed windows.  To facilitate indoor installation work, temporary closures at the south (right side of this picture) will be put in place and a temporary heating system will provide the proper environment for the workers and materials.

Recent pictures can be seen at http://picasaweb.google.com/colombierecommunity/ConstructionNov27Dec42010#

The stone wall on the chapel is coming along very nicely, too, as you can see below.